Construction underway on the $806 million rebuild of I-270

CDOT's seven-year I-270 Corridor Improvements project will replace 12 bridges dating to the 1960s and add a tolled Express Lane in each direction on the freight corridor between I-25 and I-70.

Traffic on Interstate 270 near the Vasquez Boulevard signs, in a Colorado Department of Transportation photograph from the project's environmental record. The corridor carries more than 100,000 vehicles a day, and construction on its $806 million rebuild is now underway.
Traffic on Interstate 270 near the Vasquez Boulevard signs, in a Colorado Department of Transportation photograph from the project's environmental record. The corridor carries more than 100,000 vehicles a day, and construction on its $806 million rebuild is now underway.Colorado Department of Transportation · Source

The I-270 Corridor Improvements project is in construction, according to the Colorado Department of Transportation, with Kiewit Corporation building a reconfigured freeway between Interstate 25 and Interstate 70 through Adams and Denver counties. The corridor carries more than 100,000 vehicles a day, and freight trucks account for nearly 10 percent of that traffic, according to the federal permitting record for the project.

The start of construction follows a six-year environmental review. CDOT and the Federal Highway Administration have published the project's final environmental impact statement and record of decision, which finalizes the selected alternative for roughly six miles of I-270 in Adams County. "I-270 has needed this kind of attention for a long time," CDOT Executive Director Shoshana Lew said in the announcement. "Advancing from an Environmental Assessment to a full EIS in 2023 was the right call."

An aerial view of I-270's bridges in the corridor, with the RTD commuter rail bridge alongside and downtown Denver in the distance, in a Colorado Department of Transportation photograph. Eight of the corridor's 12 bridges, those in the poorest condition, are rebuilt in the project's first phase.
An aerial view of I-270's bridges in the corridor, with the RTD commuter rail bridge alongside and downtown Denver in the distance, in a Colorado Department of Transportation photograph. Eight of the corridor's 12 bridges, those in the poorest condition, are rebuilt in the project's first phase.Colorado Department of Transportation · Source

The rebuild replaces the corridor's 12 aging bridges and adds one tolled Express Lane in each direction alongside two general-purpose lanes in each direction. The Express Lanes will be free for buses, motorcycles and carpools of three or more people. Crews will also rebuild the Vasquez Boulevard interchange, improve ramps at I-76, York Street and Quebec Street, add a continuous auxiliary lane between Vasquez Boulevard and York Street, and widen shoulders with emergency turnarounds to help clear crashes and breakdowns.

The first phase, running from October 2026 into early 2030, raises the westbound roadway along its northern edge on the stretch running from 60th Avenue toward the South Platte River Trail, and rebuilds the eight bridges in the poorest condition, among them the crossings of the South Platte River and the Burlington Ditch and the bridges at Brighton Boulevard and 60th Avenue. The first phase also reconstructs the mainline from the South Platte River to the Vasquez Boulevard ramps. Phases two and three follow from early 2030 to 2033, rebuilding the remaining mainline, the Vasquez Boulevard interchange and the York Street and 56th Avenue bridges, along with the Vasquez Boulevard bridge over Sand Creek, improvements on Sandcreek Drive and a new bicycle and pedestrian overpass.

Deteriorated bridge rail, its concrete crumbled around rusted reinforcing steel, on westbound I-270 over 60th Avenue, in a Colorado Department of Transportation photograph. The bridge is one of 12 on the corridor dating to the 1960s that the project will replace.
Deteriorated bridge rail, its concrete crumbled around rusted reinforcing steel, on westbound I-270 over 60th Avenue, in a Colorado Department of Transportation photograph. The bridge is one of 12 on the corridor dating to the 1960s that the project will replace.Colorado Department of Transportation · Source

Away from the travel lanes, the project adds four new RTD bus stops near the Quebec Street interchange, a bicycle and pedestrian bridge between East 56th Avenue and Quebec Street, and air quality monitoring, water quality ponds and wetlands mitigation along the corridor, according to CDOT.

For drivers, the early work is mostly an overnight story. CDOT lists single-lane closures overnight, from 9 p.m. to 5 a.m., on the stretch of I-270 running from 60th Avenue to the South Platte River, plus right shoulder closures on the westbound side of the same stretch and daytime flagging on Brighton Boulevard just north of the freeway. The department lists no daytime impacts on the mainline freeway.

CDOT's phasing map for the I-270 Corridor Improvements project marks the first phase, in the middle of the corridor, as active. Later phases run toward I-25 and I-70, and construction is scheduled to finish in 2033.
CDOT's phasing map for the I-270 Corridor Improvements project marks the first phase, in the middle of the corridor, as active. Later phases run toward I-25 and I-70, and construction is scheduled to finish in 2033.Colorado Department of Transportation · Source

i-270 cdot commerce city highways construction

More from Transportation

Aspen/Pitkin County Airport and its runway cross the valley floor below Aspen Highlands, in a file photograph. The airport closes on April 4, 2027, for 229 days while the runway is rebuilt 80 feet west of its current line.

Transportation

Aspen will close its airport for 229 days to rebuild a failing runway

The Roaring Fork Valley's only commercial airport shuts down on April 4, 2027, and does not reopen until November 19. The pavement is failing from below, the FAA has stopped paying for patches, and an 80-foot move west is the price of keeping federal money.

Nathan Ross · 2026-10-18

An RTD commuter rail train at Denver Union Station. The agency presented a proposed $1.34 billion expense budget for 2027 to its board's Finance and Planning Committee on Tuesday night, Oct. 13.

Transportation

RTD brings a $1.34 billion proposed 2027 budget to its board, with the deficit down to $148 million

The transit agency says cost cutting has cut its structural deficit nearly in half since 2024. Public comment runs through Dec. 1, when the board holds a hearing and considers adoption.

Nathan Ross · 2026-10-14

Interstate 70 curves along Clear Creek below Floyd Hill, with the Veterans Memorial Tunnels in the distance. Overnight closures Oct. 18-20 will move eastbound traffic onto a new bridge over the creek and pause westbound traffic at U.S. 6.

Transportation

I-70 at Floyd Hill closes overnight Oct. 18-20 as traffic shifts onto the new Clear Creek bridge

Eastbound traffic moves onto a newly completed bridge over Clear Creek on Sunday night, and westbound lanes close two more nights while crews grout the segmental bridge overhead.

Nathan Ross · 2026-10-13

Colorado TribuneTransportation